Electric Stacker is the battery power as an energy source, a motor as a power source storage device. The main structures include: batteries, motors, hydraulic pumps, cylinders, piston rods, forks, chains, controller, etc. devices. Its main function is to enhance the weight to the desired height.
2013年8月31日星期六
Bridge crane lifting operations
Bridge crane within the plant, because the top rail from the roof chord close, plus overhead cranes are larger in size and weight, it is not mechanized lifting.
SMEs often use a single mast crane lifting the overall standing, so you can improve efficiency, shorten the construction period and reduce high-altitude operations, the construction procedure is as follows.
(A) the erection of the mast
① mast mast height maximum height of the ground to the roof top of the mast to a height less operating space between the roof and the height of the mast sleepers inquiry. Minimum height should meet the needs of lifting height.
② mast mast position due to be Electric pallet jack in the carts between the two main beam bridge crane center of gravity, the car must be biased, but the mast should deviate from the centerline of plant, shown in Figure 7-8. Its offset should be based on weight carts, trolleys and trolley weight offset distance determined by calculation.
③ mast mast bottom should be compacted bottom handle, smooth, spread over two sleepers, if necessary, can be added between two sleepers rails or beams, paved area determined by calculating base endurance, ensure that the ground bear mast axial pressure.
④ mast mast erection methods used mobile cranes erect, quick and safe crane beam can also be used stand mast bracket wrench can also be used auxiliary mast vertical mast. Using the crane beam corbel Erecting the mast, to carry on the crane beam corbel force checking to ensure the transverse horizontal component does not exceed the maximum weight within the span of the bridge crane nominal weight and the amount of the sum of a trolley / 20.